On 17 August 2017, Port of Gdańsk Authority signed a construction contract with Doraco for the modernization and reconstruction of quays to streamline shipping in the Port of Gdańsk.

Aarsleff has actively participated in this project with the installation of a combi sheet pile wall made of sheet piles and steel tubes under the upgrade of Niskie BON Quay. The works were performed both onshore and offshore, from vessels, and owing to our experience in hydrotechnical projects, they were successfully completed with precision and speed. The longest steel profiles installed were as long as 18.5m and were delivered onto the site as single elements.

The construction works at Obrońców Poczty Polskiej and Mew quays will have been completed by the end of 2020 and we will soon show you more works executed by our Company under this project.