Works at Railway Line to Northern Port of Gdańsk

01-10-2015

We are now beyond halfway in the piling works at Railway Line 226 – accessway to the Northern Port of Gdańsk. We have already driven 345 pile foundations out of the total number of 550 piles to be installed for the masts of traction power network. The works are scheduled for completion in February 2016.