Modernization of 400 kV Line Ostrołęka – Olsztyn

30-06-2016

We completed installation of precast reinforced concrete piles for the foundation of 29 out of 37 towers of the 400kV Line Ostrołęka – Olsztyn. Prior to the piling works, we prepared a design of piling and working platforms, ensuring safety of works in low-bearing soil. Capacity of each pile foundation was confirmed with at least one dynamic load test.

 