Construction of Expressway S7: Piling Works at Subsection “A” Reach the Halfway Point

16-07-2015

We are now beyond halfway in the piling works executed along the Section Miłomłyn - Ostróda, Subsection „A”, under the construction of Expressway S7. The total volume of works consists in installation of nearly 30 thousand precast reinforced concrete piles with lengths ranging from 8 to 16 metres. We have already completed two out of nine engineering structures. The planned expressway starts from the existing National Road DK7, at the beginning of the bypass of Miłomłyn, and ends near Ostróda, where it will be linked to the newly constructed northern section of the bypass of Ostróda.