We are installing several dozen of  precast reinforced concrete pile foundations for the construction of 220kV power line towers, section Glinki-Recław, Zachodniopomorskie Province. The scope of works consists in piling, pile test loading, construction of access roads for pile drivers, delivery of materials, all in adverse soil conditions with high levels of underground water and in low bearing soils. In order to overcome numerous obstacles in the ground and drive piles safely at all the required location, we have to apply various non-standard technical solutions.