Berliner Wall in Gdańsk

24-04-2017

We constructed nearly 100 metres long Berliner wall with brackets at the junction of Jaśkowa Dolina and Rakoczego streets, designed as support system for 4-metre-deep excavation. Installation of the I-sections took only two working days and lagging was being provided on an on-going basis along with excavating. Upon the completion of the underground part of the building, the sections will be recovered by means of the vibratory method. This is one of the most economical solutions of deep excavation support systems.